Wapping · London · 2026–27

A home in progress.

A living record of the Parry House renovation: the money, the choices, the things still to order, and the journey from scrapbook to finished rooms.
Projected final cost£34,656
Actual / paid£13,429
Net saving / overspend—
Next milestone46 daysNon-kitchen completion · 15 Nov
Programme

The road to finished

Now
Living room and hallway nearing completion. Order time-sensitive finishing items.
15 Nov 2026
Target: everywhere except the kitchen substantially finished.
Late Nov–mid Dec
Order larger furniture with 4–6 week lead times for arrival after the kitchen works.
12 Dec 2026
Kitchen renovation starts.
10 Jan 2027
Target kitchen completion, followed by major furniture arrivals and final styling.
Next up

Actions & decisions

The most relevant upcoming purchases, decisions and project actions, prioritised so you can see what needs attention next.

Open the full action list →

Current character

Materials becoming the identity

OrangeryWarm orange joinery and architectural accents in the living room.
CorkNatural cork flooring replacing the old grey carpet downstairs.
Antique brassDoor furniture, hooks and accessories bringing continuity throughout.
Strong GreenThe hallway and stairs direction, grounded in the original scrapbook.
Wine DarkBedroom accent direction paired with warm F&B No. 59.
Hague Blue glossThe exterior front door, replacing the original bright blue.
Purchases · decisions · calls · history

Moe's actions

Your operational renovation record: what needs attention, what is underway, what has been ordered, and what is complete.

Edits save in this browser until the site is hosted
Room by room

The flat

Current specification and photographic record, with historical ideas kept separate from final decisions.

Renovation journal

Before → now

Not a fake “after” story. This records the real stages: before, preparation, joinery, paint, flooring, furnishing and eventually finished.

Physical scrapbook

Design intent

The original thinking, preserved as source material. Later confirmed decisions and installed work override early scrapbook options where the project evolved.

Candidates · inspiration · one-offs

Furniture & objects

The shortlist for the pieces that will finish the flat. New design pieces sit alongside vintage finds, with each candidate tied to a specific room and job.

Project ledger

Costs

Original / quoted£34,655.56
Actual / paid£13,429.33
Unspent vs total estimate£21,226.23

Quote vs actual

A like-for-like comparison only for items with an actual paid price. Ongoing labour is excluded until settled.
Original price of paid items—
Actually paid for those items—
Net saving / overspend—

Comparison by area

Actual spend by area

How this works now

The workbook is the historical import. New costs and labour payments can now be recorded here. When hosted with a database, this page becomes the shared source of truth across devices.

Alexia labour & payments

Imported payment schedule plus payments you record from now on.

Detailed tracker

Imported renovation ledger plus new costs added on the site.
ItemTypePriorityOwnerAreaOriginal / quotedActual paidSaving / overspendStatusNotes / product

Add item

Record labour payment

Add cost